Hard1 markMultiple Choice
PMP · Question 33 · Task 9: Integrate project planning activities
A project manager reviews the following data: CPI = 0.8, SPI = 1.2. What does this indicate about the project status?
A project manager reviews the following data: CPI = 0.8, SPI = 1.2. What does this indicate about the project status?
Answer options:
A.
Over budget and behind schedule
B.
Under budget and ahead of schedule
C.
Over budget and ahead of schedule
D.
Under budget and behind schedule
How to approach this question
Remember: Index < 1 is BAD. Index > 1 is GOOD. CPI=Cost, SPI=Schedule.
Full Answer
C.Over budget and ahead of schedule✓ Correct
C
Task 9 involves analyzing data. CPI 0.8 means you are getting 80 cents of value for every dollar (Over Budget). SPI 1.2 means you are progressing at 120% of the planned speed (Ahead of Schedule).
Common mistakes
Mixing up greater than/less than 1 meanings.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard