Hard1 markMultiple Choice
PMP · Question 32 · Task 9: Integrate project planning activities
A project manager is preparing the Project Management Plan. Which of the following is a subsidiary plan that must be integrated?
A project manager is preparing the Project Management Plan. Which of the following is a subsidiary plan that must be integrated?
Answer options:
A.
Project Charter
B.
Scope Management Plan
C.
Business Case
D.
Lessons Learned Register
How to approach this question
Distinguish between 'Plans' (how to do things) and 'Documents' (records of things).
Full Answer
B.Scope Management Plan✓ Correct
B
Task 9 involves consolidating plans. The Project Management Plan integrates all knowledge area plans (Scope, Schedule, Cost, etc.).
Common mistakes
Confusing Project Documents (Registers, Logs) with Project Plans.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard