Hard1 markMultiple Choice

PMP · Question 32 · Task 9: Integrate project planning activities

A project manager is preparing the Project Management Plan. Which of the following is a subsidiary plan that must be integrated?

Answer options:

A.

Project Charter

B.

Scope Management Plan

C.

Business Case

D.

Lessons Learned Register

How to approach this question

Distinguish between 'Plans' (how to do things) and 'Documents' (records of things).

Full Answer

B.Scope Management Plan✓ Correct
B
Task 9 involves consolidating plans. The Project Management Plan integrates all knowledge area plans (Scope, Schedule, Cost, etc.).

Common mistakes

Confusing Project Documents (Registers, Logs) with Project Plans.