PMP · Question 31 · Task 9: Integrate project planning activities
A program manager is integrating three projects: Project A (Predictive), Project B (Agile), and Project C (Hybrid). How should the program manager handle the master schedule integration?
Answer options:
Force all projects to use Microsoft Project to ensure compatibility.
Convert agile story points to hours to fit the predictive schedule.
Use milestone integration, where agile releases map to predictive milestones.
Keep the schedules completely separate and manage dependencies verbally.