For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 30
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopeTask 8ScopeWBS

    PMP · Question 30 · Task 8: Plan and manage scope

    Which of the following represents the lowest level of the Work Breakdown Structure (WBS)?

    Answer options:

    A.

    Activity

    B.

    Control Account

    C.

    Work Package

    D.

    Task

    How to approach this question

    Recall the hierarchy: WBS -> Work Package -> Activities (Schedule).

    Full Answer

    C.Work Package✓ Correct
    C
    The WBS decomposes scope down to the Work Package level. The Work Package is then further decomposed into Activities for the schedule, but Activities are NOT part of the WBS itself.

    Common mistakes

    Selecting Activity. The WBS is scope-oriented; Activities are time-oriented.
    Question 29All questionsQuestion 31

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →