Hard1 markMultiple Choice
PMP · Question 29 · Task 8: Plan and manage scope
A project manager is collecting requirements for a new hospital software. The users are busy doctors who have little time for interviews. Which techniques are MOST appropriate? (Select TWO)
A project manager is collecting requirements for a new hospital software. The users are busy doctors who have little time for interviews. Which techniques are MOST appropriate? (Select TWO)
Answer options:
A.
Focus Groups
B.
Job Shadowing / Observation
C.
Questionnaires
D.
Document Analysis
E.
Facilitated Workshops
F.
Interviews
How to approach this question
Select techniques that are passive or asynchronous, respecting the stakeholders' time constraints.
Full Answer
B,D
Task 8 involves determining requirements. When stakeholders are unavailable, observation (B) and analyzing existing artifacts (D) are the best ways to gather data without interrupting them.
Common mistakes
Selecting workshops (E) which are time-intensive.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert