PMP · Question 28 · Task 8: Plan and manage scope
During backlog refinement, the team discovers a user story is too large to fit in a single sprint. What should the project manager suggest?
Answer options:
Extend the sprint duration to accommodate the story.
Assign more developers to the story to finish it faster.
Split the story into smaller, vertical slices that deliver value.
Move the story to the Kanban board.
60 questions · hints · full answers · grading