PMP · Question 27 · Task 8: Plan and manage scope
A stakeholder directly asks a team member to add a small feature. The team member adds it because it only takes 2 hours. This is an example of:
Answer options:
Progressive Elaboration
Scope Creep
Gold Plating
Agile Adaptation