Hard1 markMultiple Choice
PMP · Question 44 · Task 12: Manage project artifacts
In an agile project, where should the team look to find the most current status of the work?
In an agile project, where should the team look to find the most current status of the work?
Answer options:
A.
Weekly Status Report
B.
Project Management Plan
C.
Information Radiator (e.g., Kanban Board)
D.
Meeting Minutes
How to approach this question
Identify the 'living' artifact.
Full Answer
C.Information Radiator (e.g., Kanban Board)✓ Correct
C
Task 12. Agile promotes transparency via Information Radiators. This is the primary source of real-time status.
Common mistakes
Looking for traditional reports (A).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard