Hard1 markMultiple Choice

PMP · Question 44 · Task 12: Manage project artifacts

In an agile project, where should the team look to find the most current status of the work?

Answer options:

A.

Weekly Status Report

B.

Project Management Plan

C.

Information Radiator (e.g., Kanban Board)

D.

Meeting Minutes

How to approach this question

Identify the 'living' artifact.

Full Answer

C.Information Radiator (e.g., Kanban Board)✓ Correct
C
Task 12. Agile promotes transparency via Information Radiators. This is the primary source of real-time status.

Common mistakes

Looking for traditional reports (A).