PMP · Question 45 · Task 13: Determine appropriate project methodology/methods and practices
A project has unclear requirements, high rates of change, and a need for frequent customer feedback. Which methodology is MOST appropriate?
A project has unclear requirements, high rates of change, and a need for frequent customer feedback. Which methodology is MOST appropriate?
Answer options:
A.
Predictive (Waterfall)
B.
Adaptive (Agile)
C.
Iterative
D.
Incremental
How to approach this question
Match characteristics (Change, Feedback, Unclear Req) to Methodology.
Full Answer
B.Adaptive (Agile)✓ Correct
Task 13 involves determining methodology. The Stacey Matrix suggests Adaptive approaches for high uncertainty/high change environments.
Common mistakes
Confusing Iterative (learning) with Adaptive (learning + speed + change handling).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert