Hard1 markMultiple Choice
PMP · Question 46 · Task 13: Determine appropriate project methodology/methods and practices
A company is transitioning from predictive to agile. The project manager notices the team is struggling to self-organize and is waiting for instructions. What should the project manager do?
A company is transitioning from predictive to agile. The project manager notices the team is struggling to self-organize and is waiting for instructions. What should the project manager do?
Answer options:
A.
Revert to assigning tasks until they are ready.
B.
Report the team's incompetence to management.
C.
Adopt a Servant Leadership style and coach them on self-management techniques.
D.
Implement a hybrid approach permanently.
How to approach this question
Select the coaching/servant-leader option.
Full Answer
C.Adopt a Servant Leadership style and coach them on self-management techniques.✓ Correct
C
Task 13 involves recommending practices. Transitioning requires coaching. The PM shifts from 'Director' to 'Servant Leader'.
Common mistakes
Reverting to command-and-control (A) because it's faster in the short term.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert