Hard1 markMultiple Choice

PMP · Question 46 · Task 13: Determine appropriate project methodology/methods and practices

A company is transitioning from predictive to agile. The project manager notices the team is struggling to self-organize and is waiting for instructions. What should the project manager do?

Answer options:

A.

Revert to assigning tasks until they are ready.

B.

Report the team's incompetence to management.

C.

Adopt a Servant Leadership style and coach them on self-management techniques.

D.

Implement a hybrid approach permanently.

How to approach this question

Select the coaching/servant-leader option.

Full Answer

C.Adopt a Servant Leadership style and coach them on self-management techniques.✓ Correct
C
Task 13 involves recommending practices. Transitioning requires coaching. The PM shifts from 'Director' to 'Servant Leader'.

Common mistakes

Reverting to command-and-control (A) because it's faster in the short term.