Hard1 markMultiple Choice
PMP · Question 47 · Task 13: Determine appropriate project methodology/methods and practices
A project manager is tailoring the project processes for a small, low-risk internal project. Which actions are appropriate? (Select TWO)
A project manager is tailoring the project processes for a small, low-risk internal project. Which actions are appropriate? (Select TWO)
Answer options:
A.
Skip the project charter to save time.
B.
Combine the Scope, Schedule, and Cost plans into a simplified Project Management Plan.
C.
Eliminate risk management entirely.
D.
Bypass the lessons learned process.
E.
Use a lightweight change control process with the sponsor as the sole approver.
F.
Remove the requirement for a Work Breakdown Structure.
How to approach this question
Select options that simplify/consolidate without removing core value/authorization.
Full Answer
B,E
Task 13 involves assessing complexity and recommending strategy. Tailoring means 'right-sizing'. Combining plans (B) and simplifying approval (E) reduces overhead without losing control.
Common mistakes
Removing essential processes (Risk, Charter) entirely.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert