Hard1 markMultiple Choice

PMP · Question 47 · Task 13: Determine appropriate project methodology/methods and practices

A project manager is tailoring the project processes for a small, low-risk internal project. Which actions are appropriate? (Select TWO)

Answer options:

A.

Skip the project charter to save time.

B.

Combine the Scope, Schedule, and Cost plans into a simplified Project Management Plan.

C.

Eliminate risk management entirely.

D.

Bypass the lessons learned process.

E.

Use a lightweight change control process with the sponsor as the sole approver.

F.

Remove the requirement for a Work Breakdown Structure.

How to approach this question

Select options that simplify/consolidate without removing core value/authorization.

Full Answer

B,E
Task 13 involves assessing complexity and recommending strategy. Tailoring means 'right-sizing'. Combining plans (B) and simplifying approval (E) reduces overhead without losing control.

Common mistakes

Removing essential processes (Risk, Charter) entirely.

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam