PMP · Question 48 · Task 13: Determine appropriate project methodology/methods and practices

A project involves developing a new pharmaceutical drug. The regulatory approval phase is rigid and linear, but the clinical trial data analysis requires rapid iteration and hypothesis testing. What is the BEST methodology?

Answer options:

A.

Pure Agile

B.

Pure Predictive

C.

Hybrid

D.

Scrum

How to approach this question

Identify conflicting needs (Rigid vs Flexible) -> Hybrid.

Full Answer

C.Hybrid✓ Correct
C
Task 13. When different phases or components have different characteristics (Stable vs Evolving), Hybrid is the correct choice.

Common mistakes

Forcing one methodology on the whole project.