Hard1 markMultiple Choice
PMP · Question 48 · Task 13: Determine appropriate project methodology/methods and practices
A project involves developing a new pharmaceutical drug. The regulatory approval phase is rigid and linear, but the clinical trial data analysis requires rapid iteration and hypothesis testing. What is the BEST methodology?
A project involves developing a new pharmaceutical drug. The regulatory approval phase is rigid and linear, but the clinical trial data analysis requires rapid iteration and hypothesis testing. What is the BEST methodology?
Answer options:
A.
Pure Agile
B.
Pure Predictive
C.
Hybrid
D.
Scrum
How to approach this question
Identify conflicting needs (Rigid vs Flexible) -> Hybrid.
Full Answer
C.Hybrid✓ Correct
C
Task 13. When different phases or components have different characteristics (Stable vs Evolving), Hybrid is the correct choice.
Common mistakes
Forcing one methodology on the whole project.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert