Hard1 markMultiple Choice
PMP · Question 49 · Task 14: Establish project governance structure
A project manager identifies a risk that exceeds the project's tolerance thresholds. The risk response requires resources beyond the project manager's authority. What should the project manager do?
A project manager identifies a risk that exceeds the project's tolerance thresholds. The risk response requires resources beyond the project manager's authority. What should the project manager do?
Answer options:
A.
Accept the risk.
B.
Escalate the risk to the project sponsor or steering committee.
C.
Use the management reserve without approval.
D.
Mitigate the risk using existing project resources.
How to approach this question
Match 'Exceeds Authority' to 'Escalate'.
Full Answer
B.Escalate the risk to the project sponsor or steering committee.✓ Correct
B
Task 14 involves defining escalation paths. Governance structures define who handles risks at what level.
Common mistakes
Trying to be a hero and handle it internally (D).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert