Hard1 markMultiple Choice

PMP · Question 50 · Task 14: Establish project governance structure

In a multi-phase project, the governance board requires a 'Phase Gate' review before funding the next phase. What is the PRIMARY purpose of this review?

Answer options:

A.

To celebrate the completion of the phase.

B.

To re-assign the project manager.

C.

To evaluate project performance and determine if the project should continue, change, or terminate.

D.

To archive project documents.

How to approach this question

Identify the 'Go/No-Go' decision point.

Full Answer

C.To evaluate project performance and determine if the project should continue, change, or terminate.✓ Correct
C
Task 14. Governance includes decision gates. The board reviews deliverables and business case validity to decide on funding the next phase.

Common mistakes

Viewing it as just a status meeting.