Hard1 markMultiple Choice
PMP · Question 50 · Task 14: Establish project governance structure
In a multi-phase project, the governance board requires a 'Phase Gate' review before funding the next phase. What is the PRIMARY purpose of this review?
In a multi-phase project, the governance board requires a 'Phase Gate' review before funding the next phase. What is the PRIMARY purpose of this review?
Answer options:
A.
To celebrate the completion of the phase.
B.
To re-assign the project manager.
C.
To evaluate project performance and determine if the project should continue, change, or terminate.
D.
To archive project documents.
How to approach this question
Identify the 'Go/No-Go' decision point.
Full Answer
C.To evaluate project performance and determine if the project should continue, change, or terminate.✓ Correct
C
Task 14. Governance includes decision gates. The board reviews deliverables and business case validity to decide on funding the next phase.
Common mistakes
Viewing it as just a status meeting.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert