PMP · Question 51 · Task 14: Establish project governance structure
An agile team wants to skip the daily stand-up because they feel it is a waste of time. How should the project manager (acting as Scrum Master) respond?
Answer options:
Allow them to skip it; they are self-organizing.
Force them to attend and take attendance.
Change it to a weekly meeting.
Explore why they feel it is a waste and help them improve the meeting's value while maintaining the practice.