Hard1 markMultiple Choice
PMP · Question 52 · Task 15: Manage project issues
A major dispute arises between two key vendors regarding the integration of their subsystems. The project is stalling. What is the BEST way for the project manager to resolve this issue?
A major dispute arises between two key vendors regarding the integration of their subsystems. The project is stalling. What is the BEST way for the project manager to resolve this issue?
Answer options:
A.
Terminate one of the contracts.
B.
Ask the legal department to sue both vendors.
C.
Facilitate a collaborative problem-solving session with both vendors to find a technical solution.
D.
Decide on the technical solution yourself and order them to implement it.
How to approach this question
Choose the collaborative, problem-solving option.
Full Answer
C.Facilitate a collaborative problem-solving session with both vendors to find a technical solution.✓ Correct
C
Task 15 involves managing issues. Collaboration is preferred over litigation or termination. The PM acts as a bridge.
Common mistakes
Resorting to legal/contractual threats immediately.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard