PMP · Question 53 · Task 15: Manage project issues
An agile team is blocked because they cannot access the test environment. The Scrum Master has tried to get access but failed. What is the NEXT step?
Answer options:
Tell the team to stop working.
Escalate the impediment to the project sponsor or management.
Ask the team to build their own environment.
Cancel the sprint.
60 questions · hints · full answers · grading