Hard1 markMultiple Choice

PMP · Question 55 · Task 16: Ensure knowledge transfer for project continuity

When should the Lessons Learned Register be updated?

Answer options:

A.

Only at the end of the project.

B.

Only at the end of each phase.

C.

Continuously throughout the project lifecycle.

D.

When the project sponsor requests it.

How to approach this question

Select the 'Continuous' option.

Full Answer

C.Continuously throughout the project lifecycle.✓ Correct
C
Task 16 involves ensuring knowledge transfer. The best practice is continuous updates so the current project benefits from the learning.

Common mistakes

Thinking Lessons Learned is only a closing activity (A).