When should the Lessons Learned Register be updated?
When should the Lessons Learned Register be updated?
Answer options:
A.
Only at the end of the project.
B.
Only at the end of each phase.
C.
Continuously throughout the project lifecycle.
D.
When the project sponsor requests it.
How to approach this question
Select the 'Continuous' option.
Full Answer
C.Continuously throughout the project lifecycle.✓ Correct
C
Task 16 involves ensuring knowledge transfer. The best practice is continuous updates so the current project benefits from the learning.
Common mistakes
Thinking Lessons Learned is only a closing activity (A).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard