Hard1 markMultiple Choice
PMP · Question 56 · Task 16: Ensure knowledge transfer for project continuity
A senior team member is leaving the project in two weeks. They possess critical tacit knowledge about the system architecture. What is the BEST way to ensure knowledge transfer?
A senior team member is leaving the project in two weeks. They possess critical tacit knowledge about the system architecture. What is the BEST way to ensure knowledge transfer?
Answer options:
A.
Ask them to write a comprehensive manual.
B.
Pair them with a junior member for shadowing and pair programming.
C.
Record a video of them explaining the system.
D.
Ask them to organize their files on the shared drive.
How to approach this question
Identify the interactive/collaborative method for 'Tacit' knowledge.
Full Answer
B.Pair them with a junior member for shadowing and pair programming.✓ Correct
B
Task 16. Tacit knowledge is hard to document. Pairing/Shadowing allows the junior member to ask questions and see the decision-making process in action.
Common mistakes
Relying on documentation (A) for tacit knowledge.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert