PMP · Question 57 · Task 16: Ensure knowledge transfer for project continuity
An agile team conducts a retrospective. What is the PRIMARY output of this meeting?
An agile team conducts a retrospective. What is the PRIMARY output of this meeting?
Answer options:
A.
A report to management.
B.
Updated velocity charts.
C.
Actionable improvement items for the next sprint.
D.
A list of complaints.
How to approach this question
Focus on 'Improvement' and 'Action'.
Full Answer
C.Actionable improvement items for the next sprint.✓ Correct
C
Task 16. Retrospectives facilitate knowledge transfer within the team to improve performance. The output is an improvement plan (Kaizen).
Common mistakes
Thinking it's a status meeting or a complaint session.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert