PMP · Question 57 · Task 16: Ensure knowledge transfer for project continuity

An agile team conducts a retrospective. What is the PRIMARY output of this meeting?

Answer options:

A.

A report to management.

B.

Updated velocity charts.

C.

Actionable improvement items for the next sprint.

D.

A list of complaints.

How to approach this question

Focus on 'Improvement' and 'Action'.

Full Answer

C.Actionable improvement items for the next sprint.✓ Correct
C
Task 16. Retrospectives facilitate knowledge transfer within the team to improve performance. The output is an improvement plan (Kaizen).

Common mistakes

Thinking it's a status meeting or a complaint session.