Hard1 markMultiple Choice

PMP · Question 58 · Task 17: Plan and manage project/phase closure or transitions

A project has been terminated early due to budget cuts. What should the project manager do FIRST?

Answer options:

A.

Release the team immediately to save money.

B.

Follow the formal project closure procedures.

C.

Delete all project files.

D.

Write a final report blaming the finance department.

How to approach this question

Terminated = Closed. Follow the closure process.

Full Answer

B.Follow the formal project closure procedures.✓ Correct
B
Task 17 involves closing the project. Early termination is a type of closure. You must document where you stopped so the work isn't wasted.

Common mistakes

Walking away without documenting (A).

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam