A project has a BAC of $200,000 and an EAC of $250,000. What is the Variance at Completion (VAC)? (Enter the number only, use a minus sign if negative)
A project has a BAC of $200,000 and an EAC of $250,000. What is the Variance at Completion (VAC)? (Enter the number only, use a minus sign if negative)
How to approach this question
VAC = BAC - EAC.
Full Answer
-50000
VAC = BAC - EAC = 200,000 - 250,000 = -50,000. Negative means over budget.
Common mistakes
EAC - BAC (wrong sign).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert