PMP · Question 59 · Task 17: Plan and manage project/phase closure or transitions

A project has a BAC of $200,000 and an EAC of $250,000. What is the Variance at Completion (VAC)? (Enter the number only, use a minus sign if negative)

How to approach this question

VAC = BAC - EAC.

Full Answer

-50000
VAC = BAC - EAC = 200,000 - 250,000 = -50,000. Negative means over budget.

Common mistakes

EAC - BAC (wrong sign).