Hard1 markMultiple Choice
PMP · Question 60 · Task 17: Plan and manage project/phase closure or transitions
Before declaring a project closed, what is the FINAL activity the project manager must ensure is complete?
Before declaring a project closed, what is the FINAL activity the project manager must ensure is complete?
Answer options:
A.
Releasing the team.
B.
Acceptance of deliverables.
C.
Archiving project documents and updating organizational process assets.
D.
Paying the final invoices.
How to approach this question
Identify the administrative finale.
Full Answer
C.Archiving project documents and updating organizational process assets.✓ Correct
C
Task 17. Closure involves transition and archiving. Updating OPAs ensures the organization learns. This is the final administrative signal that the project is done.
Common mistakes
Confusing Deliverable Acceptance (Scope Validation) with Project Closure.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard