PMP · Question 60 · Task 17: Plan and manage project/phase closure or transitions

Before declaring a project closed, what is the FINAL activity the project manager must ensure is complete?

Answer options:

A.

Releasing the team.

B.

Acceptance of deliverables.

C.

Archiving project documents and updating organizational process assets.

D.

Paying the final invoices.

How to approach this question

Identify the administrative finale.

Full Answer

C.Archiving project documents and updating organizational process assets.✓ Correct
C
Task 17. Closure involves transition and archiving. Updating OPAs ensures the organization learns. This is the final administrative signal that the project is done.

Common mistakes

Confusing Deliverable Acceptance (Scope Validation) with Project Closure.