PMP · Question 008 · Task 10: Manage project changes
A project manager is leading a large predictive project. A key stakeholder requests a change to the scope that will add significant value but delay the schedule by two weeks. The project is currently on the critical path. What should the project manager do FIRST?
Answer options:
Submit a change request to the Change Control Board (CCB).
Implement the change because it adds significant business value.
Analyze the impact of the change on cost, quality, and resources.
Reject the change because the project is on the critical path.