For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 008
    Hard1 markMultiple Choice
    Task 10: Manage project changesProcessChange Management

    PMP · Question 008 · Task 10: Manage project changes

    A project manager is leading a large predictive project. A key stakeholder requests a change to the scope that will add significant value but delay the schedule by two weeks. The project is currently on the critical path. What should the project manager do FIRST?

    Answer options:

    A.

    Submit a change request to the Change Control Board (CCB).

    B.

    Implement the change because it adds significant business value.

    C.

    Analyze the impact of the change on cost, quality, and resources.

    D.

    Reject the change because the project is on the critical path.

    How to approach this question

    Follow the formal change control sequence: Identify -> Analyze -> Submit -> Approve/Reject.

    Full Answer

    C.Analyze the impact of the change on cost, quality, and resources.✓ Correct
    C
    Task 10 (Manage Changes) in a predictive environment follows a strict sequence. Analysis (C) provides the necessary information for the CCB to make a decision.

    Common mistakes

    Choosing A (Skipping analysis) or B (Gold plating/Scope creep).
    Question 007All questionsQuestion 009

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →