Hard1 markMultiple Choice
PMP · Question 009 · Task 10: Build shared understanding
An agile team is struggling to reach a consensus on the estimation of user stories during planning poker. The debate is consuming too much time. Which TWO actions should the project manager (acting as Scrum Master) take?
An agile team is struggling to reach a consensus on the estimation of user stories during planning poker. The debate is consuming too much time. Which TWO actions should the project manager (acting as Scrum Master) take?
Answer options:
A.
Decide the story points based on the average of the team's estimates.
B.
Ask the Product Owner to assign the estimates.
C.
Ask the outliers (highest and lowest estimators) to explain their reasoning.
D.
Remove the user stories from the sprint to discuss later.
E.
Facilitate a discussion to build shared understanding of the story requirements.
F.
Use the highest estimate to be safe.
How to approach this question
Select TWO. Focus on facilitation and building consensus, not dictating.
Full Answer
C, E
The goal is to Build Shared Understanding (Task 10). By asking outliers to speak (C) and facilitating requirement clarification (E), the PM helps the team converge on a consensus.
Common mistakes
Choosing A or B (Taking ownership away from the team).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert