    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 010
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodologyProcessMethodology

    PMP · Question 010 · Task 13: Determine appropriate project methodology

    A project manager is assigned to a project with a high degree of uncertainty regarding requirements. The organization traditionally uses predictive methods, but the sponsor is open to new approaches. Which methodology is MOST appropriate for this scenario?

    Answer options:

    A.

    Predictive

    B.

    Agile

    C.

    Waterfall

    D.

    Phased-Gate

    How to approach this question

    Match 'High Uncertainty' to 'Agile'.

    Full Answer

    B.Agile✓ Correct
    B
    Task 13 requires determining the methodology. High uncertainty and undefined requirements are the primary indicators for selecting an Agile/Adaptive approach.

    Common mistakes

    Choosing A because the organization is traditional (Methodology should fit the project, not just history).
    Question 009All questionsQuestion 011

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →