PMP · Question 011 · Task 1: Plan and manage project compliance
During the execution of a project, a new regulation is passed that impacts the project's compliance requirements. The project is 80% complete. What should the project manager do FIRST?
During the execution of a project, a new regulation is passed that impacts the project's compliance requirements. The project is 80% complete. What should the project manager do FIRST?
Answer options:
A.
Continue with the current plan as the law was passed after the project started.
B.
Assess the impact of the new regulation on the project scope and deliverables.
C.
Immediately implement the necessary changes to ensure compliance.
D.
Close the project and start a new one to address the compliance needs.
How to approach this question
New Regulation -> Assess Impact -> Plan Response.
Full Answer
B.Assess the impact of the new regulation on the project scope and deliverables.✓ Correct
B
Business Environment Task 1 focuses on compliance. When the environment changes (Task 3), the PM must assess the impact on scope before taking action.
Common mistakes
Choosing A (Ignoring law) or C (Acting without planning).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert