For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 6Question 15
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valuebusiness valueMVPscope managementstakeholder involvement

    PMP · Question 15 · Task 1: Execute project with the urgency required to deliver business value

    A software development project has an opportunity to deliver a minimum viable product (MVP) three months ahead of the original schedule, which could capture significant market advantage. However, this would require descoping some planned features. What should the project manager do FIRST?

    Answer options:

    A.

    Proceed with the MVP delivery since early market entry provides competitive advantage

    B.

    Analyze the business value of early delivery versus the value of the descoped features with key stakeholders

    C.

    Maintain the original scope and schedule to ensure all planned features are delivered

    D.

    Ask the development team to work overtime to deliver all features on the accelerated timeline

    How to approach this question

    Look for approaches that focus on business value analysis and stakeholder involvement in value-based decisions.

    Full Answer

    B.Analyze the business value of early delivery versus the value of the descoped features with key stakeholders✓ Correct
    B
    Delivering business value requires analyzing trade-offs between early delivery and feature completeness, involving stakeholders in value-based decision making.

    Common mistakes

    Making unilateral decisions about scope changes, or rigidly adhering to original plans without considering value opportunities.
    Question 14All questionsQuestion 16

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →