PMP · Question 15 · Task 1: Execute project with the urgency required to deliver business value
A software development project has an opportunity to deliver a minimum viable product (MVP) three months ahead of the original schedule, which could capture significant market advantage. However, this would require descoping some planned features. What should the project manager do FIRST?
Answer options:
Proceed with the MVP delivery since early market entry provides competitive advantage
Analyze the business value of early delivery versus the value of the descoped features with key stakeholders
Maintain the original scope and schedule to ensure all planned features are delivered
Ask the development team to work overtime to deliver all features on the accelerated timeline
100 questions · hints · full answers · grading