PMP · Question 36 · Task 1: Manage conflict
A project manager is facilitating a conflict between two team members who have different approaches to solving a technical problem. The conflict is affecting team morale and project progress. Which TWO actions should the project manager take FIRST to manage this conflict effectively?
A project manager is facilitating a conflict between two team members who have different approaches to solving a technical problem. The conflict is affecting team morale and project progress. Which TWO actions should the project manager take FIRST to manage this conflict effectively?
Answer options:
Create a safe environment where both team members can express their perspectives without judgment
Make a decision about which technical approach to use to resolve the conflict quickly
Separate the team members to work on different parts of the project
Help both team members understand the underlying interests and concerns behind their positions
Escalate the conflict to the functional managers of both team members
Schedule individual meetings with each team member to hear their concerns privately
How to approach this question
Full Answer
Common mistakes