Hard1 markMultiple Choice
PMP · Question 37 · Task 2: Lead a team
A project manager is leading a team that includes both experienced senior developers and junior developers new to the technology stack. The project requires innovative solutions and the senior developers tend to dominate discussions. What leadership approach should the project manager use FIRST?
A project manager is leading a team that includes both experienced senior developers and junior developers new to the technology stack. The project requires innovative solutions and the senior developers tend to dominate discussions. What leadership approach should the project manager use FIRST?
Answer options:
A.
Directive leadership to ensure decisions are made efficiently
B.
Laissez-faire leadership to let the experienced developers guide the project
C.
Collaborative leadership to ensure all team members contribute their perspectives and ideas
D.
Coaching leadership focused on developing the junior developers' skills
How to approach this question
Consider which leadership style would best engage all team members and leverage their diverse perspectives for innovation.
Full Answer
C.Collaborative leadership to ensure all team members contribute their perspectives and ideas✓ Correct
C
Collaborative leadership actively engages all team members regardless of experience level, which is essential for innovation and team development in diverse teams.
Common mistakes
Choosing directive approaches that don't engage junior members, or laissez-faire approaches that allow domination by senior members.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert