Hard1 markMultiple Choice
Task 2: Lead a teamleadership stylescollaborative leadershipteam diversityinnovation

PMP · Question 37 · Task 2: Lead a team

A project manager is leading a team that includes both experienced senior developers and junior developers new to the technology stack. The project requires innovative solutions and the senior developers tend to dominate discussions. What leadership approach should the project manager use FIRST?

Answer options:

A.

Directive leadership to ensure decisions are made efficiently

B.

Laissez-faire leadership to let the experienced developers guide the project

C.

Collaborative leadership to ensure all team members contribute their perspectives and ideas

D.

Coaching leadership focused on developing the junior developers' skills

How to approach this question

Consider which leadership style would best engage all team members and leverage their diverse perspectives for innovation.

Full Answer

C.Collaborative leadership to ensure all team members contribute their perspectives and ideas✓ Correct
C
Collaborative leadership actively engages all team members regardless of experience level, which is essential for innovation and team development in diverse teams.

Common mistakes

Choosing directive approaches that don't engage junior members, or laissez-faire approaches that allow domination by senior members.