PMP · Question 43 · Task 8: Negotiate project agreements
A project manager is negotiating a contract modification with a critical vendor who is requesting additional compensation due to scope changes. The vendor has valid justifications, but the requested amount exceeds the project manager's approval authority. Which TWO actions should the project manager take FIRST?
Answer options:
Analyze the vendor's cost justification and validate the scope changes that triggered the request
Immediately escalate to the sponsor since the amount exceeds approval authority
Explore alternative solutions that might address the vendor's concerns within existing budget constraints
Accept the vendor's request since they are critical to project success
Reject the request to maintain project budget constraints
Document the negotiation for future reference and lessons learned
100 questions · hints · full answers · grading