For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 6Question 44
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder managementrelationship buildingtrust rebuildingcollaboration

    PMP · Question 44 · Task 9: Collaborate with stakeholders

    A key stakeholder who was initially supportive of the project has become increasingly critical and is publicly questioning project decisions. This is affecting team morale and other stakeholder confidence in the project. What should the project manager do FIRST?

    Answer options:

    A.

    Address the stakeholder's concerns publicly to demonstrate transparency and project confidence

    B.

    Document the stakeholder's behavior and escalate to the project sponsor

    C.

    Schedule a private meeting with the stakeholder to understand their concerns and work to rebuild trust

    D.

    Limit the stakeholder's access to project information to prevent further public criticism

    How to approach this question

    Look for collaborative approaches that seek to understand stakeholder concerns and rebuild relationships rather than confrontational or avoidance strategies.

    Full Answer

    C.Schedule a private meeting with the stakeholder to understand their concerns and work to rebuild trust✓ Correct
    Effective stakeholder collaboration requires understanding changing stakeholder positions and working proactively to rebuild trust and alignment when relationships deteriorate.

    Common mistakes

    Choosing confrontational approaches, premature escalation, or avoidance strategies that don't address the underlying relationship issues.
    Question 43All questionsQuestion 45

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →