Hard1 markMultiple Choice
PMP · Question 11 · Task 3: Support team performance
An agile team's velocity has dropped for three consecutive sprints. The team members are working long hours and morale is low. What should the project manager do FIRST?
An agile team's velocity has dropped for three consecutive sprints. The team members are working long hours and morale is low. What should the project manager do FIRST?
Answer options:
A.
Add more resources to the team to help them meet the timeline.
B.
Offer a bonus for completing the next sprint on time.
C.
Discuss the trend in the retrospective to identify root causes and potential solutions.
D.
Reduce the scope of the project immediately.
How to approach this question
When performance drops in Agile, the first step is always to inspect and adapt via the Retrospective.
Full Answer
C.Discuss the trend in the retrospective to identify root causes and potential solutions.✓ Correct
C
The PM should not solve the problem FOR the team. The team must analyze the drop in velocity during the retrospective to determine if it's due to technical debt, burnout, unclear requirements, etc.
Common mistakes
Jumping to solutions (A, B, D) before analysis.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert