PMP · Question 12 · Task 3: Support team performance
A team member consistently submits deliverables that meet the minimum requirements but lack attention to detail, causing rework for others. The project manager has a feedback session scheduled. What is the BEST approach?
Answer options:
Use the 'sandwich' method: praise, criticism, praise.
Wait for the annual performance review to document the pattern.
Compare the team member's work to a high-performing peer's work.
Describe the specific behavior, the impact on the team, and ask for their perspective.
60 questions · hints · full answers · grading