PMP · Question 27 · Task 6: Build a team
A key technical lead is leaving the project in two weeks. The project is halfway through. Which TWO actions should the PM take to ensure knowledge transfer?
Answer options:
Ask the lead to write a comprehensive manual of everything they know.
Facilitate knowledge sharing sessions (e.g., brown bag, shadowing) with the remaining team members.
Pair the departing lead with a successor for the remaining time.
Cancel the lead's remaining tasks so they can relax.
Record the lead performing their daily tasks.