For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP People Domain Practice ExamQuestion 33
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsNegotiationProcurement

    PMP · Question 33 · Task 8: Negotiate project agreements

    A project manager is negotiating a service level agreement (SLA) with a vendor. The vendor is insisting on a price that is 10% over budget. The PM knows the vendor wants to enter this new market segment. What is the BEST negotiation strategy?

    Answer options:

    A.

    Demand the price be lowered or threaten to cancel.

    B.

    Focus on the vendor's interest in market entry and offer a case study/testimonial in exchange for the lower price.

    C.

    Split the difference (pay 5% over budget).

    D.

    Accept the higher price and cut scope elsewhere.

    How to approach this question

    Look for the 'Win-Win' option that addresses the other party's underlying interests.

    Full Answer

    B.Focus on the vendor's interest in market entry and offer a case study/testimonial in exchange for the lower price.✓ Correct
    B
    Effective negotiation involves identifying shared interests. The vendor wants market entry (marketing value); the PM wants a lower price. Trading these creates value for both sides.

    Common mistakes

    Thinking negotiation is a zero-sum game (A or C).
    Question 32All questionsQuestion 34

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →