PMP · Question 34 · Task 8: Negotiate project agreements
An agile team is struggling to reach an agreement on the Definition of Done (DoD). The testers want strict criteria, while developers argue it will slow them down. How should the PM facilitate this negotiation?
Answer options:
Decide the DoD for them based on industry standards.
Side with the testers to ensure quality.
Facilitate a session to visualize the cost of technical debt vs. velocity, helping them find a balance they can commit to.
Let them operate without a DoD until they agree.