PMP · Question 35 · Task 8: Negotiate project agreements
A project manager is preparing for a complex negotiation with a client regarding a scope change. Which TWO actions should the PM take during the preparation phase?
Answer options:
Determine the BATNA (Best Alternative to a Negotiated Agreement).
Prepare a script to read during the meeting.
Refuse to meet until the client agrees to the price.
Analyze the client's priorities, constraints, and underlying interests.
Tell the team the change is already approved.