Hard1 markMultiple Choice
PMP · Question 35 · Task 8: Negotiate project agreements
A project manager is preparing for a complex negotiation with a client regarding a scope change. Which TWO actions should the PM take during the preparation phase?
A project manager is preparing for a complex negotiation with a client regarding a scope change. Which TWO actions should the PM take during the preparation phase?
Answer options:
A.
Determine the BATNA (Best Alternative to a Negotiated Agreement).
B.
Prepare a script to read during the meeting.
C.
Refuse to meet until the client agrees to the price.
D.
Analyze the client's priorities, constraints, and underlying interests.
E.
Tell the team the change is already approved.
How to approach this question
Select the standard negotiation preparation steps: Know yourself (BATNA) and Know your opponent (Analysis).
Full Answer
A,D
Preparation is 90% of negotiation. Identifying your BATNA ensures you don't accept a bad deal. Analyzing the other party helps you craft a good deal.
Common mistakes
Thinking preparation means writing a script (B).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert