    PracticePMI PMP®PMP People Domain Practice ExamQuestion 49
    Hard1 markMultiple Choice
    Task 12: Define team ground rulesGround RulesAgile

    PMP · Question 49 · Task 12: Define team ground rules

    A new agile team is forming. The project manager wants to ensure the team has a clear set of behavioral expectations. What should the PM do?

    Answer options:

    A.

    Write a list of rules and email it to the team.

    B.

    Facilitate a session for the team to co-create their Team Charter/Ground Rules.

    C.

    Use the HR employee handbook as the ground rules.

    D.

    Ask the Scrum Master to enforce the standard company rules.

    How to approach this question

    Ground rules must be created BY the team, not FOR the team.

    Full Answer

    B.Facilitate a session for the team to co-create their Team Charter/Ground Rules.✓ Correct
    The Team Charter (containing ground rules) is a foundational document for agile teams. It must be created collaboratively so the team feels ownership of their norms.

    Common mistakes

    Dictating rules (A).
    Question 48All questionsQuestion 50

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →