Hard1 markMultiple Choice
PMP · Question 50 · Task 12: Define team ground rules
A team established a ground rule to 'be on time for meetings'. However, the senior architect is consistently 10 minutes late. The team is annoyed but says nothing. What should the PM do?
A team established a ground rule to 'be on time for meetings'. However, the senior architect is consistently 10 minutes late. The team is annoyed but says nothing. What should the PM do?
Answer options:
A.
Publicly reprimand the architect at the next meeting.
B.
Ignore it since the architect is senior.
C.
Remind the team of their ground rules and encourage them to hold each other accountable.
D.
Change the meeting time to accommodate the architect.
How to approach this question
The goal is self-policing. The PM nudges the team to enforce their own rules first.
Full Answer
C.Remind the team of their ground rules and encourage them to hold each other accountable.✓ Correct
C
In a mature team, members hold each other accountable. The PM should first encourage this peer accountability before intervening directly, as this strengthens the team.
Common mistakes
Acting as the 'police' immediately (A) or giving special treatment (B).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert