For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP People Domain Practice ExamQuestion 50
    Hard1 markMultiple Choice
    Task 12: Define team ground rulesGround RulesAccountability

    PMP · Question 50 · Task 12: Define team ground rules

    A team established a ground rule to 'be on time for meetings'. However, the senior architect is consistently 10 minutes late. The team is annoyed but says nothing. What should the PM do?

    Answer options:

    A.

    Publicly reprimand the architect at the next meeting.

    B.

    Ignore it since the architect is senior.

    C.

    Remind the team of their ground rules and encourage them to hold each other accountable.

    D.

    Change the meeting time to accommodate the architect.

    How to approach this question

    The goal is self-policing. The PM nudges the team to enforce their own rules first.

    Full Answer

    C.Remind the team of their ground rules and encourage them to hold each other accountable.✓ Correct
    In a mature team, members hold each other accountable. The PM should first encourage this peer accountability before intervening directly, as this strengthens the team.

    Common mistakes

    Acting as the 'police' immediately (A) or giving special treatment (B).
    Question 49All questionsQuestion 51

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →