Hard1 markMultiple Choice
PMP · Question 51 · Task 12: Define team ground rules
Which TWO elements are typically included in a Team Charter?
Which TWO elements are typically included in a Team Charter?
Answer options:
A.
Detailed project schedule.
B.
Conflict resolution process.
C.
Individual salary information.
D.
Meeting guidelines and communication norms.
E.
The final product specifications.
How to approach this question
Select items related to 'behavior' and 'process', not 'product' or 'schedule'.
Full Answer
B,D
The Team Charter defines the social contract: values, decision-making criteria, conflict resolution, and meeting norms. It establishes the environment for the team.
Common mistakes
Confusing Project Charter (high level authorization) with Team Charter (team norms).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert