Hard1 markMultiple Choice

PMP · Question 51 · Task 12: Define team ground rules

Which TWO elements are typically included in a Team Charter?

Answer options:

A.

Detailed project schedule.

B.

Conflict resolution process.

C.

Individual salary information.

D.

Meeting guidelines and communication norms.

E.

The final product specifications.

How to approach this question

Select items related to 'behavior' and 'process', not 'product' or 'schedule'.

Full Answer

B,D
The Team Charter defines the social contract: values, decision-making criteria, conflict resolution, and meeting norms. It establishes the environment for the team.

Common mistakes

Confusing Project Charter (high level authorization) with Team Charter (team norms).