PMP · Question 52 · Task 12: Define team ground rules

Midway through a project, the team complains that the daily stand-up is taking too long and isn't valuable. What should the PM do?

Answer options:

A.

Cancel the stand-ups.

B.

Facilitate a discussion to revisit the ground rules for the stand-up and adjust the format.

C.

Enforce a strict 15-minute timer without discussion.

D.

Take over the meeting and run it yourself.

How to approach this question

If a process is broken, Inspect and Adapt.

Full Answer

B.Facilitate a discussion to revisit the ground rules for the stand-up and adjust the format.✓ Correct
B
The team owns their process. If the ground rules for the stand-up aren't working, the PM should facilitate a change to those rules to restore value.

Common mistakes

Enforcing the rule rigidly (C) even when it's failing.