    PracticePMI PMP®PMP People Domain Practice ExamQuestion 52
    Hard1 markMultiple Choice
    Task 12: Define team ground rulesGround RulesAgile

    PMP · Question 52 · Task 12: Define team ground rules

    Midway through a project, the team complains that the daily stand-up is taking too long and isn't valuable. What should the PM do?

    Answer options:

    A.

    Cancel the stand-ups.

    B.

    Facilitate a discussion to revisit the ground rules for the stand-up and adjust the format.

    C.

    Enforce a strict 15-minute timer without discussion.

    D.

    Take over the meeting and run it yourself.

    How to approach this question

    If a process is broken, Inspect and Adapt.

    Full Answer

    B.Facilitate a discussion to revisit the ground rules for the stand-up and adjust the format.✓ Correct
    The team owns their process. If the ground rules for the stand-up aren't working, the PM should facilitate a change to those rules to restore value.

    Common mistakes

    Enforcing the rule rigidly (C) even when it's failing.
    Question 51All questionsQuestion 53

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard