Hard1 markMultiple Choice
PMP · Question 38 · Task 9: Collaborate with stakeholders
A project manager realizes that a key stakeholder has a different understanding of the project's success criteria than the project team. The project is 50% complete. What is the BEST way to align expectations?
A project manager realizes that a key stakeholder has a different understanding of the project's success criteria than the project team. The project is 50% complete. What is the BEST way to align expectations?
Answer options:
A.
Show the stakeholder the signed Project Charter and insist they follow it.
B.
Conduct a workshop to review the success criteria and negotiate any necessary adjustments to the scope or acceptance criteria.
C.
Change the project to match the stakeholder's new view.
D.
Ignore the difference and deliver what was originally planned.
How to approach this question
When expectations diverge, realign through dialogue and formal change management if needed.
Full Answer
B.Conduct a workshop to review the success criteria and negotiate any necessary adjustments to the scope or acceptance criteria.✓ Correct
B
Collaboration requires continuous alignment. If a gap is found, the PM must facilitate a conversation to close it, rather than relying solely on past documents or ignoring the issue.
Common mistakes
Being rigid (A) or too accommodating (C).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert