    PracticePMI PMP®PMP People Domain Practice ExamQuestion 40
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersStakeholder EngagementAgile

    PMP · Question 40 · Task 9: Collaborate with stakeholders

    The Product Owner (PO) is frequently absent from sprint planning and reviews, causing the team to guess at requirements. The PO claims they are too busy with customers. What is the PM's BEST response?

    Answer options:

    A.

    Act as the proxy PO and make decisions for the team.

    B.

    Cancel the sprints until the PO returns.

    C.

    Meet with the PO to explain the impact of their absence on value delivery and collaborate on a schedule that works.

    D.

    Report the PO to the sponsor.

    How to approach this question

    Coach/Collaborate first. Explain 'Impact' to motivate change.

    Full Answer

    C.Meet with the PO to explain the impact of their absence on value delivery and collaborate on a schedule that works.✓ Correct
    C
    The PM needs to collaborate with the PO to ensure the team is supported. Explaining the 'impact' (wasted effort, wrong product) is a powerful way to influence the PO to prioritize the team.

    Common mistakes

    Taking over the PO role (A).
    Question 39All questionsQuestion 41

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →