Hard1 markMultiple Choice
PMP · Question 41 · Task 10: Build shared understanding
A project manager notices that during technical discussions, the marketing representative stays silent. Later, the marketing rep complains that the product won't meet customer needs. What is the likely root cause of this misunderstanding?
A project manager notices that during technical discussions, the marketing representative stays silent. Later, the marketing rep complains that the product won't meet customer needs. What is the likely root cause of this misunderstanding?
Answer options:
A.
The marketing rep is not interested in the project.
B.
The use of technical jargon excluded the marketing rep from the shared understanding.
C.
The marketing rep is passive-aggressive.
D.
The technical team is hostile.
How to approach this question
Look for communication barriers (Language/Jargon) as the source of misunderstanding.
Full Answer
B.The use of technical jargon excluded the marketing rep from the shared understanding.✓ Correct
B
Building shared understanding requires accessible language. Technical jargon creates a barrier (noise) that prevents non-technical stakeholders from engaging, leading to misunderstandings.
Common mistakes
Blaming the person (A/C) instead of the communication style.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert