Hard1 markMultiple Choice
PMP · Question 42 · Task 10: Build shared understanding
An agile team needs to decide on a database schema. Three members want Option A, two want Option B. The debate is circling. What technique should the PM suggest to reach a shared decision?
An agile team needs to decide on a database schema. Three members want Option A, two want Option B. The debate is circling. What technique should the PM suggest to reach a shared decision?
Answer options:
A.
Majority vote.
B.
PM decides.
C.
Fist of Five voting.
D.
Coin toss.
How to approach this question
Select the specific agile consensus technique.
Full Answer
C.Fist of Five voting.✓ Correct
C
Fist of Five is a participatory decision-making technique that builds shared understanding by allowing team members to express their level of confidence/agreement, prompting further discussion if consensus isn't met.
Common mistakes
Choosing Majority Vote (A). In Agile, we strive for Consensus, not just majority.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert