Hard1 markMultiple Choice
PMP · Question 43 · Task 10: Build shared understanding
A project manager is kicking off a complex partnership project. Which TWO activities will BEST help build a shared understanding of the project goals among all partners?
A project manager is kicking off a complex partnership project. Which TWO activities will BEST help build a shared understanding of the project goals among all partners?
Answer options:
A.
Emailing the Statement of Work to all partners.
B.
Co-creating a Project Charter in a facilitated workshop.
C.
Defining a glossary of common terms and acronyms.
D.
Asking partners to sign a non-disclosure agreement.
E.
Assigning the PM's organization as the lead for all decisions.
How to approach this question
Select activities that involve interaction and language definition.
Full Answer
Co-creation (B) ensures alignment on vision. A glossary (C) ensures alignment on language. Both are foundational for shared understanding.
Common mistakes
Relying on documents (A) without interaction.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert