    Hard1 markMultiple Choice
    Task 10: Build shared understandingCommunicationKickoff

    PMP · Question 43 · Task 10: Build shared understanding

    A project manager is kicking off a complex partnership project. Which TWO activities will BEST help build a shared understanding of the project goals among all partners?

    Answer options:

    A.

    Emailing the Statement of Work to all partners.

    B.

    Co-creating a Project Charter in a facilitated workshop.

    C.

    Defining a glossary of common terms and acronyms.

    D.

    Asking partners to sign a non-disclosure agreement.

    E.

    Assigning the PM's organization as the lead for all decisions.

    How to approach this question

    Select activities that involve interaction and language definition.

    Full Answer

    B,C
    Co-creation (B) ensures alignment on vision. A glossary (C) ensures alignment on language. Both are foundational for shared understanding.

    Common mistakes

    Relying on documents (A) without interaction.
    Question 42All questionsQuestion 44

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →